DIS - Case Record for 98-0621-RR-FED Skip to main content
      
      
CASE NUMBER: 98-0621-RR-FED
CASE DESCRIPTION: FEDERAL CROSSING PROTECTION/1998
DOCUMENT SIGNED ON: 6/30/2024
DATE OF SERVICE: ________________________________________
02/24/2000 Entry closing this case of record. (1 pg.)
02/07/2000 Memo filed by J. Reinhardt, PUCO staff, stating that all forty-seven grade crossing warning projects have been in- stalled and inspected for this case, and recommending that this case be closed of record. (4 pgs.)
09/21/1999 Request to withdraw its request for an extension of time in which to complete the grade crossing warning device installation projects, filed on behalf of Norfolk Southern Railway Co. by R. Noe. (1 pg.)
09/16/1999 Copy of letter dated September 11, 1999, concerning the in-service notification from Mr. Jeff Stair, Norfolk Southern's Project engineer, for the Jefferson County, South River Road grade crossing warning project, sub- mitted by J. Reinhardt, PUCO staff. (2 pgs.)
08/13/1999 Request for an extension of time to complete grade crossing warning device installation projects in Belmont and Jeffer- son Counties filed by R. Noe. (1 pg)
05/25/1999 Request for an extension of 30 days for the highway grade crossing installation at Erie Street, filed on behalf of Wheeling & Lake Erir Railway Co. by D. Reinsel. (1 pg.)
05/21/1999 Memo recommending that the request of WLE for a 30 day ex- tension for this project be approved, filed by J. Reinhardt, PUCO staff. (1 pg.)
05/21/1999 Memo recommending that the request of Conrail for a 30 day extension for this project be approved, filed by J. Reinhardt, PUCO staff. (1 pg.)
05/21/1999 Entry granting W&LE's request for a 30-day extension of time for the project. (AE) (2 pgs.)
05/21/1999 Entry granting Conrail's request for a 30-day extension of time for the project. (AE) (2 pgs.)
05/19/1999 Request for an extension of time of 30 days to June 21, 1999 to complete the project, filed on behalf of Conrail by P. Kaufmann. (1 pg.)
05/12/1999 Entry ordering that N&W be granted until December 21, 1999, to complete the grade crossing improvement project located at Seneca County, Main Street Pleasant Township. (2 pgs.)
05/07/1999 Entry ordering that Conrail's request for a 30-day extension of time be granted. (AE) (1 pg.)
05/04/1999 Memo filed by J. Reinhardt, PUCO staff, recommending that the 30 day extension be approved. (3 pgs.)
05/04/1999 Letter from D. J. Sands, Conrail, reducing their request for an extension of time to 30 day, June 20, 1999, to complete the work. (2 pgs.)
04/26/1999 Request for extension of time filed by R. Noe. (2 pgs)
04/23/1999 Request for extension of time filed by R. Noe on behalf of Norfolk Southern Railway Company. (1 pg)
03/23/1999 Request for an extension of time for the installation of the active warning system at Bunty Station Road, filed on behalf of CSX Transportation by R. Frederick. (1 pg.)
03/22/1999 Response letter to Mr. Randall G. Frederick, CSX Trans- poration, filed by R. Marvin, PUCO staff. (1 pg.)
03/18/1999 Correspondence to David J. Sands, Conrail, regarding the request for extension of time, filed by R. Marvin, PUCO staff. (1 pg.)
03/18/1999 Request for extension of time of 60 days to complete the projects, filed on behalf of Conrail by D. Sands. (2 pgs.)
03/11/1999 Request for an extension of time for completion of the installation of an active warning system at Flanders Avenue, filed on behalf of CXS by R. Frederick. (1 pg.)
02/04/1999 Entry ordering that projects for the installation of addi- tional protective devices be authorized for the public grade crossings identified in Finding 5 and Finding 6; that, where applicable, the preliminary engineering and/or con- struction costs associated with these installation projects be funded as set forth in Findings 5 and 6; that the instal- lation projects be completed by February 4, 2000. (5 pgs.)
01/29/1999 Memo from J. Reinhardt, PUCO staff, listing the various grade crossings that were approved per Ohio Development Rail Commission and Federal Highway Administration for flashing light signals and roadway gates. (1 pg.)
01/21/1999 Entry ordering that the Commission order issued in this case on December 30, 1998 be amended as set forth in Findings 3 and 4. (3 pgs.)
12/30/1998 Entry ordering that projects for the installation of addi- tional protective devices be authorized for the public grade crossings indentified in Finding 4; that the preliminary engineering and construction costs associated with these installation projects be funded as set further in Finding 5; that railroads file with the Commission's Railroad Division as soon as possible, site plans, cost estimates, and pro- posed time schedules for the installation of automatic pro- tective devices at these crossings as set forth in Finding 7; that the installation projects be completed by December 30, 1999. (5 pgs.)
12/21/1998 List of grade crossings that have been diagnostic surveyed and recommended for upgrade of warning devices under the 1998 Federal Grade Crossing Warning Program, filed on behalf of the PUCO staff by J. Reinhardt. (1 pg.)
09/24/1998 Entry ordered the projects for installation of additional protective devices be authorized for public grade crossings identified in Finding No. 4; the preliminary engineering and construction costs associated with these installation projects be funded as set forth in Finding No. 5; the rail- roads file with the Commission as soon as possible the site plans, cost estimates and proposed time schedules for the installation of devices as set forth in Finding No. 7. That all installation be completed at these crossings no later than September 24, 1999. (5 pgs.)
05/27/1998 Service Notice
05/21/1998 Entry ordering that projects for the installation of additional protective devices be authorized for the public grade crossings identified in Finding 5 and Finding 6; that the preliminary engineering and construction costs associated with these installation projects be funded as set fur- forth in Finding 7; that the railroads file with the Commission mission's Railroad Division as soon as possible site plans, cost estimates, and proposed time schedules for the instalation of automatic protective devices at the crossings as set forth in Finding 6; that the installation projects be completed by May 21, 1999. (6 pgs.)
05/21/1998 Entry ordering that the projects for the installation of protective devices be authorized in accordance with Findings (5) and (6); the preliminary engineering and construction costs associated with these installation projects be founded as set further in Finding (7);that the installation projects be completed at these crossings no later than May 21,1999; that the railroad notify the Commission's Railroad Division, Ohio Rail Development Commission and ODOT's District Office of the scheduled date to start construction and activation of warning project.
04/14/1998 In the matter of the implementation of the 1998 Federal Crossing Protection Program. (1 pg.)