Date Filed | Summary | Pages |
10/05/2001 | Memo closing this case of record. | 2 |
07/07/1999 | ICN #0067 Notification that construction of the Riverview- Elkem 138 kV Transmission Line was completed on September 28, 1998 and the line was energized on October 30, 1998, filed on behalf of applicant by T. Zitterbart. (1 pg.) | 1 |
12/31/1998 | ICN #0066 Mandate, judgment entry, and appeal from the Ohio Power Siting Board, filed on behalf of The Supreme Court of Ohio. (2 pgs.) | 2 |
12/01/1998 | ICN #0065 Application for dismissal of its appeal, filed on behalf of applicant by C. Schraff. (4 pgs.) | 4 |
11/23/1998 | ICN #0064 Entry ordering that the Board finds that since all outstanding issues have been resolved, there is no longer a need for the Board Staff to file a report in this docket; the Board finds that the proposed project will be consistent with plans for expansion of the regional power grid and will serve the interest of electric systems econ- omy and reliability; further, the Board finds that to the extent that the agreement requires any additional constru- ction, Monongahela shall comply with the conditions of the certificate issued in this case. (3 pgs.) | 3 |
11/19/1998 | ICN #0063 Joint stipulation for dismissal filed on behalf of applicant by G. Jack; Elkem Metals by F. King; and AMP- Ohio by J. Bentine. (1 pg.) | 1 |
10/30/1998 | ICN #0062 Notice of Appeal filed on behalf of applicant by C. Schraff. (7 pgs.) | 7 |
09/29/1998 | ICN #0061 Study proposal submitted to Allegheny Power by ABB, filed on behalf of applicant by G. Jack. (23 pgs.) | 23 |
09/18/1998 | ICN #0060 Cost estimates for the four options depicted in the ABB Report, filed on behalf of applicant by G. Jack. (5 pgs.) | 5 |
09/01/1998 | ICN #0059 Reliability Study of Sectionalizing Equipment for Gorsuch Power Station filed. (52 pgs.) (FILED 8/31/98) | 52 |
08/31/1998 | ICN #0057 Portion of the Ohio Power Siting Board-directed study in connection with this case, filed by D. Rogers. (41 pgs.) | 41 |
08/31/1998 | ICN #0058 Entry denying Amp-Ohio's application for rehear- ing and denying each of Monongahela's requests for rehear- ing; that the Board's July 13, 1998 Order is clarified in regards to the Staff's involvement in determining whether a breaker or switch(es) shall be installed or the switch(es) improved pursuant to Finding 9. (9 pgs.) | 9 |
08/28/1998 | ICN #0056 Motion for finding of violation of R.C. Section 4906.98 and for other relief and memorandum in support filed on behalf of American Municipal Power by J. Bentine. (19 pgs.) | 19 |
08/27/1998 | ICN #0055 Entry ordering that Monongahela's request for an extension is granted and that the studies and other infor- mation shall be filed by August 31, 1998. (AE) (2 pgs.) | 2 |
08/24/1998 | AMP-Ohio's memorandum contra Monongahela Power Company's Application for Rehearing, filed by J. Bentine. (5 pgs) | 5 |