10/05/2005 | Letter stating that the project on the Muskingum-Central 345 kV Line Reconductor was completed May 31, 2002 filed by S. Williams on behalf of Ohio Power Company dba American Electric Power. | 1 |
09/09/2005 | Letter stating that this project has been completed filed by S. Williams on behalf of American Electric Power Service Corporation. | 1 |
01/30/2002 | Construction notice stating construction will begin on this project on 2/11/02 filed by J. Heppner, Transmission Line Engineering | 1 |
10/23/2001 | In the matter of the construction notice of American Electric Power Company for the Muskingum-Central 345 kV Reconductor Project. | 10 |