10/05/2005
|
Letter stating that the project on the Muskingum-Central 345 kV Line Reconductor was completed May 31, 2002 filed by S. Williams on behalf of Ohio Power Company dba American Electric Power. |
09/09/2005
|
Letter stating that this project has been completed filed by S. Williams on behalf of American Electric Power Service Corporation. |
01/30/2002
|
Construction notice stating construction will begin on this project on 2/11/02 filed by J. Heppner, Transmission Line Engineering |
10/23/2001
|
In the matter of the construction notice of American Electric Power Company for the Muskingum-Central 345 kV Reconductor Project. |