CASE NUMBER: 01-2730-EL-BNR
CASE DESCRIPTION: AEP/OHIO POWER
DOCUMENT SIGNED ON: 5/8/2024
DATE OF SERVICE: ________________________________________
10/05/2005 Letter stating that the project on the Muskingum-Central 345 kV Line Reconductor was completed May 31, 2002 filed by S. Williams on behalf of Ohio Power Company dba American Electric Power.
09/09/2005 Letter stating that this project has been completed filed by S. Williams on behalf of American Electric Power Service Corporation.
01/30/2002 Construction notice stating construction will begin on this project on 2/11/02 filed by J. Heppner, Transmission Line Engineering
10/23/2001 In the matter of the construction notice of American Electric Power Company for the Muskingum-Central 345 kV Reconductor Project.