Case Record For:

88-1092-EL-BTX

File a Public Comment
Case Title: CENTERIOR ENERGY
Status: AR-Archived
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 7/21/1988
Date Closed: 10/29/1990
Printable Docket Card Service List
View All
1 - 15 of 104 documents 1 /  7 
Date FiledSummaryPages
10/16/2000ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates.13
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates 7
10/16/2000ICN #0102 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.)6
11/04/1991ICN #0100 Letter stating that Inland-Lake Shore Trans- mission Line field construction activities were completed on October 21, 1991, line was energized on October 25, 1991, for testing purposes, and commercial operation is anticipated to begin later this year, filed on behalf of applicant by M. Ams.0
03/22/1991ICN #0099 Letter to Mr. M. J. Ams, Centerior Energy, stating that applicant may proceed with construction of the portion of the plan and profile drawings which were submitted March 12, 1991, filed on behalf of OPSB staff by J. Kennedy.0
03/21/1991ICN #0098 Memorandum contra to the request for reconsidera- tion and re-opening of hearing procedures filed by Gallo Display, Inc., et. al., filed on behalf of CEI by C. Smith.0
03/18/1991ICN #0097 Set of engineering drawings for the single circuit section of the transmission line and for grade construction at the Inland and Lake Shore stations filed on behalf of applicant by W. Ams.0
03/11/1991ICN #0096 Request for reconsideration and reopening of hearing procedures filed on behalf of Gallo Displays, Inc.; Beverage Distributors, Inc.; Milner Electric Company; G.R.Z. Properties Company; and Hexagraphics, Inc. by R. Siegel.0
02/20/1991ICN #0095 Letter notifying the Commission that measures have been developed to deal with possible interference with existing radio antennas owned by the Ohio Department of Transportation and Boothe Broadcasting adjacent to the subject transmission line, filed on behalf of applicant by M. Ams.0
02/14/1991ICN #0094 Letter stating that construction of the portion of the project represented on the drawing may proceed, filed on behalf of OPSB staff by J. Kennedy.0
02/01/1991ICN #0093 One set of engineering drawings for the double circuit section of the transmission line and for the circuit breaker foundations at Inland, filed on behalf of applicant by J. Ams.0
10/31/1990ICN# 0092 Letter filed on behalf of the OPSB stating that the engineering drawings are consistent with the description of the certificated project filed by J. Kennedy.0
10/31/1990ICN# 0091 Drawings of the proposed construction filed on behalf of the applicant by A. Ams.0
10/29/1990ICN #0090 Opinion, Order, and Certificate issued approving the joint stipulation submitted on the amended application and ordering the certificate of Environmental Compatibility and Public Need be issued. (OPSB)0
09/27/1990ICN #0089 Transcript filed for hearing held 9/18/90, (RG) l0 pgs., Submitted.0
 
1 /  7 
      
      
Attorney General:
Attorney Examiner: