DIS - Case Record for 09-1914-EL-BNR Skip to main content

Case Record For:

09-1914-EL-BNR

File a Public Comment
Case Title: AMERICAN TRANSMISSION SYSTEMS INC/BABB-EAST AKRON 138 KV TRANSMISSION LINE RELOCATION FOR THE MARTHA AVENUE ROUNDABOUT
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 12/4/2009
Date Closed: 3/20/2015
Printable Docket Card Service List
View All
1 - 5 of 5 documents 1 /  1 
Date FiledSummaryPages
03/20/2015Case Action Form to Close Cases effective 3/20/2015.6
05/24/2010Construction notice that the Babb-East Akron 138 kV Transmission Line Relocation for the Martha Avenue Roundabout project was completed on approximately May 15, 2010 filed on behalf of FirstEnergy by S. Humphrys. 1
05/21/2010Notice that construction on the Babb-East Akron project is expected to begin on or shortly after May 13, 2010 filed by T. Krauss on behalf of FirstEnergy Service Company.1
01/07/2010Staff Investigation and recommendation filed. 1
12/04/2009In the matter of the construction notice of American Transmission Systems, Inc, for Babb-East Akron 138kV transmission line relocation for the Martha Avenue Roundabout.19
 
1 /  1 
      
      
Attorney General: