Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
05/24/2010 | Construction notice that the Babb-East Akron 138 kV Transmission Line
Relocation for the Martha Avenue Roundabout project was completed on approximately May 15, 2010 filed on behalf of FirstEnergy by S. Humphrys. | 1 |
05/21/2010 | Notice that construction on the Babb-East Akron project is expected to begin on or shortly after May 13, 2010 filed by T. Krauss on behalf of FirstEnergy Service Company. | 1 |
01/07/2010 | Staff Investigation and recommendation filed. | 1 |
12/04/2009 | In the matter of the construction notice of American Transmission Systems, Inc, for Babb-East Akron 138kV transmission line relocation for the Martha Avenue Roundabout. | 19 |