DIS - Case Record for 09-1914-EL-BNR Skip to main content
      
      
CASE NUMBER: 09-1914-EL-BNR
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS INC/BABB-EAST AKRON 138 KV TRANSMISSION LINE RELOCATION FOR THE MARTHA AVENUE ROUNDABOUT
DOCUMENT SIGNED ON: 5/10/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
05/24/2010 Construction notice that the Babb-East Akron 138 kV Transmission Line Relocation for the Martha Avenue Roundabout project was completed on approximately May 15, 2010 filed on behalf of FirstEnergy by S. Humphrys.
05/21/2010 Notice that construction on the Babb-East Akron project is expected to begin on or shortly after May 13, 2010 filed by T. Krauss on behalf of FirstEnergy Service Company.
01/07/2010 Staff Investigation and recommendation filed.
12/04/2009 In the matter of the construction notice of American Transmission Systems, Inc, for Babb-East Akron 138kV transmission line relocation for the Martha Avenue Roundabout.