Date Filed | Summary | Pages |
10/11/2001 | Entry closing cases this case of record. | 2 |
09/27/2001 | Memorandum recommending that the legal staff proceed with an entry to close this case of record, filed by L. Dalton, PUCO staff. | 1 |
07/19/2000 | Entry ordering that the agreement is adopted by the Commis- sion; that N&W submit for Commission approval site plans and cost estimates for the projects within 90 days of this entry; that N&W proceed with construction of the project as set forth in the agreement, with construction to be completed by June 16, 2000. | 2 |
07/13/2000 | Entry ordered, NSR's time limit for completion of the crossing closure project be extended to 9/14/00. | 2 |
07/13/2000 | Entry ordered, NSR's time limit for completion of the crossing closure project be extended to 9/14/00. | 2 |
07/13/2000 | Entry ordered, NSR's time limit for completion of the crossing closure project be extended to 9/14/00. (2 pgs.) | 2 |
06/19/2000 | Entry ordered, NSR's time limit for completion of the crossing closure project be extended to 9/14/00. | 2 |
06/16/2000 | Entry ordering that the completion dates for this project be extended 30 days, until July 16, 2000. (AE) (2 pgs.) | 2 |
06/15/2000 | Request letter on behalf of Norfolk Southern Railway Co. (NSR) for an extension of time in which to complete the closures of the grade crossings at Eban Street (AAR No. 476-795H), Liberty Street (AAR No. 746-815S), Fair Street (AAR No. 476-812W), and Clinton Street (AAR No. 476-809N) in Findlay, Ohio. Filed by R. Noe | 3 |
06/15/2000 | Letter regarding extension request. (1 pg) | 1 |
06/15/2000 | Request letter on behalf of Norfolk Southern Railway Co. (NSR) for an extension of time in which to complete the closures of the grade crossings at Eban Street (AAR No. 476-795H), Liberty Street (AAR No. 746-815S), Fair Street (AAR No. 476-812W), and Clinton Street (AAR No. 476-809N) in Findlay, Ohio. Filed by R. Noe (3 pgs) | 3 |
06/16/1999 | Entry ordering that the agreement is adopted by the Commis- sion; that N&W submit for Commission approval site plans and cost estimates for the projects within 90 days of this entry; that N&W proceed with construction of the project as set forth in the agreement, with construction to be com- pleted by June 16, 2000. (5 pgs.) | 5 |
06/04/1999 | In the matter of a request for the installation of flashing lights and roadway gates at Blanchard Street (476-796P) with a road closure at Eben Street (476-795H), City of Findlay, Hancock County, Norfolk & Western Railway. (15 pgs.) | 15 |