10/11/2001
|
Entry closing cases this case of record. |
09/27/2001
|
Memorandum recommending that the legal staff proceed with an entry to close this case of record, filed by L. Dalton, PUCO staff. |
01/06/2000
|
Entry ordering that NS Commence construction as a cantilever only, to be completed by January 7, 2001. |
12/16/1999
|
Letter relative to the construction of cantilever crossing protection at Monroe Street, given approval by City of Bellevue, G. Haynes. |
12/03/1999
|
Letter to J. Reinhardt, PUCO Staff, approving the construction of cantilever crossing protection at Monroe Street, filed on behalf of the City of Bellevue by K. Shaffer. |
01/22/1999
|
Entry granting extension of time to 2/19/99 to complete installation of the three projects identified in Finding (1) (SF) (2 pgs) |
01/19/1999
|
Memo from J. Reinhardt, PUCO staff, stating that staff recommends that W&LE be granted an additional 30 days within which to complete the State Route 57 project. (2 pgs.) |
01/13/1999
|
Letter requesting an extension till January 31, 1999, filed by D. Reinsel. (1 pg) |
01/13/1999
|
Letter requesting an extension till Feburary 15, 1999, filed by D. Reinsel. (1 pg) |
01/13/1999
|
Letter requesting a deadline extension to March 18, 1999, filed by D. Reinsel. (1 pg) |
12/23/1998
|
Entry ordering that the request for extensions of time to complete the installation of the projects identified in Finding 1 is granted. (AE) (2 pgs.) (ISSUED 12/22/98 INCORRECTLY IN CASE NO. 98-637-GA-AEC) |
12/17/1998
|
Memo, with attached letter dated December 15, 1998, from Dan Reinsel requesting a 30 day extension of the three projects, filed by J. Reinhardt, PUCO staff. (8 pgs.) |
09/24/1998
|
Entry ordering that N&W's request for an extension of time to October 18, 1998 to complete this project is granted. (SF) |
09/23/1998
|
Request for extension of time until October 18, 1998 to complete the improvement because of required engineering changes in the field, filed by Walter Dissen. |
09/23/1998
|
Request of Norfolk and Western Railway for a 30 day extension on project. |
07/07/1998
|
Entry ordering that Norfolk and Western Railway's request for an indefinite extension of the completion date for this project is granted; that the Commission's Railroad Division advise the Commission on a monthly basis of the status of this project. (3 pgs.) |
06/25/1998
|
Memo recommending to grant the extension request which was made on June 15, 1998, filed by J. Reinhardt, PUCO staff. (1 pg.) |
06/18/1998
|
Additional information filed on behalf of the City of Bellevue by G. Haynes. (1 pg.) |
06/17/1998
|
Letter requesting that the time for installation be stayed indefinitely, filed on behalf of Norfolk & Western Railway Co. by W. Dissen. (9 pgs.) |
12/18/1997
|
Entry ordering that the projects for the installation of additional protective devices be authorized for the public grade crossings indentified in Findings 5 and 6; that the installation project be completed by December 18, 1998. (7 pgs.) |
12/08/1997
|
Memo stating crossings should be processed thru the normal federal program filed by J. Reinhardt, PUCO staff. (2 pgs.) |
09/18/1997
|
Entry ordering that projects for the of additional protective devices be authorized for the public grade crossings identified in finding 4, it is further ordered that the preliminary engineering and construction costs associated with these installation projects be funded as set in finding 5, it is further ordered that in accordance with staff's recommendations, the railroads file with the Commission's railroad division as soon as possible, site plans, cost estimates, and proposed time schedules for the installation of automatic protective devices at these crossings as set forth in finding 7, it is further ordered that unless otherwise notified these railroads commence with the acquisition of materials and construction upon submission of the required plans and estimates and that the installation projects be completed at these crossing no later that September 18, 1998. (5 pgs.) |
08/27/1997
|
Entry ordering that projects for the installation of addi- tional protective devices be authorized for the public grade crossings indentified in Finding 4, to be completed by August 28, 1998. (5 pgs.) |
08/19/1997
|
Memo requesting that an entry be issued authorizing pre- lininary engineering and construction deadlines for the grade crossings mentioned, filed by J. Reinhardt, PUCO staff. (1 pg.) |
06/26/1997
|
Entry ordering that projects for the installation of addi- tional devices be authorized for the public grade crossings identified in Finding 4; that the preliminary engineering and construction costs associated with these installation projects be funded as set furthin in Finding 5; that the railroads file with the Commission's Railroad Division as soon as possible, site plans, cost estimates, and proposed time schedules for the installation of automatic protective devices at these crossings, to be completed no later than June 26, 1998. (7 pgs.) |
06/13/1997
|
In the matter of the implementation of the 1997 federal crossing protection program. (1 pg.) |