Date Filed | Summary | Pages |
06/10/2004 | Letter to Mr. Lambeck stating that the construction on the project was completed on May 28, 2004, filed on behalf of applicant by T. Krauss. | 1 |
10/21/2003 | Letter in response to the Letter of Notification, filed on behalf of applicant by T. Krauss. | 1 |
03/29/2002 | Letter in response to Ohio Edison's Letter of Notification, filed on behalf of American Transmission System by T. Krauss. | 1 |
02/12/2001 | Status Report filed by T. Krauss on behalf of ATSI. | 1 |
12/13/1994 | ICN #0004 Letter to Mr. B. L. Codispoti in response to his Letter of Notification, filed by K. Wissman, OPSB staff. (1 pg.) | 0 |
12/12/1994 | ICN #0003 Investigation report approving letter of notifi- cation, filed by J. O'Dell, PUCO staff. (1 pg.) | 0 |
11/02/1994 | ICN #0002 Transmittal letters addressed to the government representatives of the city of Elyria, Amherst Township, Brownhelm Township, Elyria Township, Sheffield Township, and Lorain County, filed on behalf of applicant by B. Cod- ispoti. (23 pgs.) | 0 |
11/02/1994 | ICN #0001 In the matter of the Letter of Notification of Ohio Edison Company for construction of additional facil- ities, Beaver-Johnson 138 kV project. (68 pgs.) | 0 |