05/31/1995 | ICN #0006 Letter stating that this project was completed August 1994, filed on behalf of applicant by E. Mikkelsen. (1 pg.) | 0 |
08/31/1994 | ICN #0005 Letter stating that construction on this project was completed and the line was energized on 8/17/94, filed on behalf of applicant by T. Denzler, P.E. (1 pg.) | 0 |
05/05/1994 | ICN #0004 Letter informing the Commission that this project is scheduled to begin on May 2, 1994, filed on behalf of applicant by T. Denzler. | 0 |
02/28/1994 | ICN #0003 Investigation report approving letter of notifi- cation, filed by L. Winget, J. O'Dell, and R. Yerian, OPSB staff. | 0 |
02/28/1994 | ICN #0002 Response to letter of notification, filed by K. Wissman, OPSB staff. | 0 |
01/14/1994 | INC #0001 In the matter of the Letter of Notification filed by Centerior Service Company on behalf of The Toledo Edison Company for the Hunt-Wesson Tap. | 0 |
|