Date Filed | Summary | Pages |
02/26/2018 | Return Mail, attempted not known, unable to forward. | 1 |
02/15/2018 | Service Notice | 3 |
02/15/2018 | Entry ordered That the application to transfer the certificates from AES
Generation to Tait Generating be granted in accordance with Paragraph 12. | 4 |
12/22/2017 | Request of AES Ohio Generation, LLC to transfer and of Tait Electric Generation Station, LLC to receive and assume certificates issued by the OPSB electronically filed by Mr. Randall V Griffin on behalf of AES Ohio Generation, LLC and Tait Electric Generating Station, LLC. | 12 |
12/22/2017 | Request of AES Ohio Generation, LLC to transfer and of Tait Electric Generating Station, LLC to receive and assume Certificates issued by the OPSB electronically filed by Mr. Randall V Griffin on behalf of AES Ohio Generation, LLC and Tait Electric Generating Stations, LLC. | 12 |
02/10/2016 | Notification of AES Ohio Generation, LLC of name change. Prior company name was DPL Energy, LLC electronically filed by Mr. Randall V Griffin on behalf of AES Ohio Generation, LLC | 2 |
02/07/2002 | Additional information filed on behalf of applicant by D. Specht. | 2 |
08/27/2001 | PUCO notification for construction 2nd report filed on behalf of applicant by D. Specht. | 2 |
02/07/2000 | Service Notice. | 4 |
02/07/2000 | ICN #0090 Entry ordering that the certificate of environmental compatibility and public need previously granted to DP&L for the construction and operation of three turbine units at the Tait Generating Station in Case No. 92-1475-EL-BGN shall be transferred to DPLE; that the certificate granted to DP&L for the construction and operation of two natural gas pipelines in Case No. 93-1049-GA-BTX shall also be transferred to DPLE; that, as a result of these transfers, DPLE shall be bound by and comply with all terms and conditions of these two certificates. | 3 |
12/29/1999 | ICN #089 Request for approval the transfer of a power siting certificate filed by E. Rizer on behalf of Dayton Power and Light Company. | 4 |
12/23/1999 | ICN #088 Request for approval the transfer of a power siting certificate filed by E. Rizer on behalf of Dayton Power and Light Company. (Fax) | 4 |
12/31/1998 | ICN #087 Letter stating that commercial operation for Tait Unit #3 began on December 31, 1998, filed on behalf of Dayton Power & Light by S. Miller. | 1 |
11/25/1998 | ICN #086 Letter stating that construction for Tait Unit #3 ended on November 19, 1998, filed on behalf of Dayton Power & Light by S. Miller | 1 |
09/17/1997 | ICN #085 Letter stating that construction for Tait Unit #3 began on September 9, 1997, filed on behalf of Dayton Power & Light by A. Farrell. | 1 |