10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
02/24/1993 | ICN #0005 Letter informing Commission that construction on this project was completed on January 18, 1993, filed on behalf of applicant by M. Ams. | 0 |
08/25/1992 | ICN #0004 Letter stating that the planned date of initial construction on this project is August 19, 1992, filed on behalf of applicant by M. Ams. | 0 |
03/11/1992 | ICN #0003 Investigation report Letter of Notification filed on behalf of the OPSB staff. | 0 |
03/11/1992 | ICN #0002 Response to Letter of Notification filed on behalf of the OPSB by J. Kennedy. | 0 |
01/28/1992 | ICN #0001 In the matter of the Letter of Notification filed by Centerior Service Company on behalf of The Cleveland Electric Illuminating Company for The Plain Dealer Supply Line. | 0 |