Date Filed | Summary | Pages |
03/30/2000 | Entry ordering that the completion date for this project be extended until June 1, 2001. (2 pgs.) | 2 |
03/13/2000 | Memo filed by F. Netting, PUCO staff, recommending that the completion date for the Galbraith Road project be extended to June 30, 2001. (1 pg.) | 1 |
02/28/2000 | Entry ordering that the completion date for this project be extended 30 days, until April 5, 2000. (AE) (2 pgs.) | 2 |
02/22/2000 | Memo filed by J. Reinhardt, PUCO staff, approving the extension requested by Mr. C. J. Hurm. (1 pg.) | 1 |
02/16/2000 | Request for a one year extension to complete the instal- lation of the Hamilton County, Galbraith Road project, filed on behalf of Indiana & Ohio Railway System by C. Hurm. (1 pg.) | 1 |
03/05/1999 | Entry ordering that the project site plans and costs estimates submitted by I&O are approved under the con- ditions set forth in the ORDC memo; that I&O complete installation of the projects by March 6, 2000. (AE) (2 pgs.) | 2 |
03/01/1999 | Memo filed by J. Reinhardt, PUCO staff, containing the construction authorization for Galbraith Road and Plain- field Road grade crossing warning projects. (5 pgs.) | 5 |
09/25/1997 | Entry ordering that the stipulation be approved; that I&O complete installation of both projects by October 30, 1997. (2 pgs.) | 2 |
09/11/1997 | Stipulation filed on behalf of Indiana & Ohio Rail System and Indiana & Ohio Railroad by M. Burkhart; and the PUCO staff by R. Marvin. (4 pgs.) | 5 |
09/11/1997 | Stipulation filed on behalf of Railroad Division by M. Burkhart and R. Marvin. | 5 |
08/14/1997 | Entry ordering that the requests of the Indiana & Ohio Railway Company for an extension of time within which to complete the installation projects at Sugar Grove Road and Lincoln Avenue in the city of Lancaster be denied; that the projects be completed as soon as possible; schedu- ling a hearing at 10:00 a.m. on August 28, 1997, at the Commission offices. (3 pgs.) | 3 |
08/06/1997 | Entry ordering that the request of the Indiana & Ohio Railway for a 30-day extension of time within which to complete the installation project at Robison Road in the city of Cincinnati be granted; that the project be completed by September 4, 1997. (AE) (2 pgs.) | 2 |
07/08/1997 | Memo from J. Reinhardt, PUCO staff, with attached letter from Donald E. Clark, Indiana and Ohio Railroad, request- ing a 30 day extension for the warning project, filed. (2 pgs.) | 2 |
06/25/1997 | Copy of letter dated June 24, 1997, from Donald Clark, Indiana & Ohio Rail System, concerning a request of an extension on the installation of grade crossing warning devices at Sugar Grove Road, Lancaster, Ohio, filed by J. Reinhardt, PUCO staff. (2 pgs.) | 2 |
03/13/1997 | Entry ordering that the request of the Indiana and Ohio Railroad for an extension of time within which to com- plete the Kemper Road installation project is granted to the extent set forth herein; that until the installation project has been completed, I&O warn of its train movements through the crossing through the use of temporary flashing light signals or by flagging the crossing. (2 pgs.) | 2 |