Date Filed | Summary | Pages |
12/06/1990 | Memo from R. Gooden, PUCO staff, stating that this case is closed. | 0 |
02/22/1990 | ICN #0005 Letter of notification stating that construction on this project has been completed and that the line was energized on 2/13/90, filed on behalf of applicant by J. Schrader. | 0 |
02/14/1990 | ICN# 0004 Letter filed on behalf of the applicant stating that the construction will begin February 11, 1990 filed by J. Schrader. | 0 |
12/11/1989 | ICN# 003 Letter filed on behalf of the OPSB stating that L. Winger and S. Coe inspected the site and it qualifies for a letter of notification filed by J. Kennedy. | 0 |
12/11/1989 | ICN# 0002 Letter filed on behalf of the OPSB stating that the application qualifies for the letter of Notification and an invoice for the direct cost is forthcoming filed by J. Kennedy. | 0 |
11/27/1989 | ICN# 0001 Application of Ohio Power Company for a Board Letter of Notification for the Akron-Canton 138Kv line conductor replacement. | 0 |