09/29/2023 | Correspondence of Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 21 |
09/28/2023 | Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 108 |
09/05/2023 | Staff Report of Investigation electronically filed by Ms. Allison Renick on behalf of Staff of OPSB. | 8 |
08/23/2023 | Response To OPSB Staff's First Data Request electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 6 |
06/14/2023 | Letter of Notification Application for the West Dover 138 kV Transmission Line Relocation Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 93 |
06/14/2023 | In the Matter of the Pre-Application Notification Letter for the West Dover 138 kV Transmission Line Relocations Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |