Date Filed | Summary | Pages |
09/07/2023 | Approved NOI Renewal (OEPA), Approved Building Permit (City of Amherst), Plan Commission Approval (City of Amherst) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 14 |
03/13/2023 | Correspondence - Ohio EPA Construction Stormwater General Permit Approval letter, electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 3 |
03/02/2023 | Notification of the Department of Army Nationwide Permit No. 57 electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 8 |
01/13/2023 | Service Notice (Staff Report). | 2 |
01/13/2023 | Staff Report of Investigation electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB. | 7 |
12/08/2022 | Response to OPSB Data Requests electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 5 |
12/01/2022 | Notice of Proof of Compliance with Service and Public Distribution Requirements electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 33 |
11/22/2022 | Letter of Notification Application for the Amherst 2nd Source Reinforcement Project (Part 2 of 2) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 487 |
11/22/2022 | Letter of Notification Application for the Amherst 2nd Source Reinforcement Project (Part 1 of 2) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC.
| 251 |
11/17/2022 | In the Matter of Pre-Application Notification Letter for the Amherst Second Source Reinforcement 138 kV Transmission Line Project electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. | 2 |