Date Filed | Summary | Pages |
11/18/2022 | Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
11/03/2022 | Service Notice (Staff Report). | 2 |
11/03/2022 | Staff Report of Investigation electronically filed by Ms. Allison Renick on behalf of Staff of OPSB and Ms. Allison Renick. | 6 |
11/01/2022 | Proof of Compliance, Newspaper Submission, electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 4 |
10/21/2022 | Supplemental Information Provided electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
10/19/2022 | Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 19 |
10/14/2022 | Letter of Notification Vine-City of Columbus West 138 kV Transmission Line Relocation Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 49 |
10/05/2022 | In the Matter of the Pre-Application Notification Letter for the Vine-City of Columbus West 138kV Transmission Line Relocation Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 3 |