Date Filed | Summary | Pages |
11/14/2022 | Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
10/05/2022 | Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 108 |
09/13/2022 | Service Notice. | 2 |
09/13/2022 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
08/31/2022 | Arboles Station, Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 5 |
06/23/2022 | Notice of Proof of Compliance with Notice Requirements electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
06/21/2022 | Letter of Notification for Arboles Station 138kv Transmission Line Adjustment Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 227 |
06/21/2022 | Amended Pre-Application Notification Regarding the Arboles Station Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 3 |