Date Filed | Summary | Pages |
06/02/2021 | Miami Fort to
Tanners Creek Rebuild Project
Notification of Completion of Construction and In-Service Date electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/19/2021 | Proof of publication for the Miami Fort to Tanners Creek Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 4 |
02/18/2021 | Duke Energy Ohio, Inc.'s Letter Accepting Conditions of Approval electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/16/2021 | Service Notice | 2 |
02/16/2021 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
02/11/2021 | Duke Energy Ohio, Inc.'s Response to Staff Data Request 04-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/05/2021 | Duke Energy Ohio, Inc.'s Response to Staff Data Request 03-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/03/2021 | Duke Energy Ohio, Inc.'s Response to Staff Data Request 02-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/02/2021 | Duke Energy Ohio, Inc. Response to Staff Data Request 01-003 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/02/2021 | Duke Energy Ohio, Inc. Response to Staff Data Request 01-002 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/02/2021 | Duke Energy Ohio, Inc. Response to Staff Data Request 01-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
02/01/2021 | Correspondence Duke Energy Inc. Miami Fort to Tanners Creek Rebuild Project Proof of Service electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 12 |
01/25/2021 | Application Miami Fort to Tanners Creek Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 104 |
01/20/2021 | In the matter of the Pre-Application Notification Letter for the Miami Fort to Tanners Creek Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 3 |