Date Filed | Summary | Pages |
02/01/2021 | Service Notice. | 3 |
02/01/2021 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
01/29/2021 | Notice of supplemental information and associated exhibit for the Sporn-Kyger Creek 345 kV Pole Installation Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 3 |
11/16/2020 | Notice of Proof of Compliance and associated exhibits for the Sporn-Kyger Creek 345 kV Pole Installation Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 14 |
11/09/2020 | Construction Notice Application for the Sporn-Kyger Creek 345 kV Pole Installation Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 15 |
10/30/2020 | In the Matter of Pre-Application Notification Letter for the Sporn-Kyger Creek 345 kV Pole Installation Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 2 |