Date Filed | Summary | Pages |
08/24/2021 | Notification of Completion of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
10/09/2020 | Service Notice | 3 |
10/09/2020 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
07/27/2020 | Notice of Proof of Compliance and Associated Exhibits for the Hyatt – Genoa Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 18 |
07/17/2020 | Construction Notice Application for the Hyatt – Genoa Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. | 13 |
07/02/2020 | In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company. | 2 |