02/01/2021 | Notice of In-Service Date for the Bethel-Sawmill 138 kV Transmission Line Project (Brookside-Sawmill) electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
05/21/2020 | Notice of Start of Construction electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
04/02/2020 | Notice of supplemental information for the Bethel-Sawmill 138 kV Transmission Line Project (Brookside-Sawmill) electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 3 |
01/30/2020 | Staff Report of Investigation (dated January 28, 2020) electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
01/28/2020 | Service Notice | 2 |
01/08/2020 | Notice of Adjustment for the Bethel-Sawmill 138 kV Transmission Line Project (Brookside-Sawmill) and associated exhibits electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 4 |
11/21/2019 | Proof of Pub electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 4 |
11/12/2019 | Proof of Compliance Letter and associated exhibits for the Amendment Application for the Bethel-Sawmill 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 19 |
11/05/2019 | In the matter of the Letter of Notification for the Bethel-Sawmill 138kV Transmission Line Project (Brookside-Sawmill) electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 162 |