Case Title: Ashtabula 138kV Substation Expansion Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 10/23/2018
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
06/28/2019Notice of construction completed on June 25, 2019 filed on behalf of FirstEnergy Service Company by N. Bryksenkova.1
04/04/2019Notice stating that Construction of Ashtabula 138 kV Substation Expansion Project is expected to begin on or shortly after April 9, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
11/19/2018Service Notice2
11/19/2018Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
11/02/2018Application of American Transmission Systems, Incorporated for the Construction Notice of Ashtabula 138 kV Substation Expansion filed by N. Bryksenkova.34
10/23/2018In the matter of the Pre-Application Notification Letter for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.2