CASE NUMBER: 18-1594-EL-BNR
CASE DESCRIPTION: Ashtabula 138kV Substation Expansion Project
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
06/28/2019 Notice of construction completed on June 25, 2019 filed on behalf of FirstEnergy Service Company by N. Bryksenkova.
04/04/2019 Notice stating that Construction of Ashtabula 138 kV Substation Expansion Project is expected to begin on or shortly after April 9, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
11/19/2018 Service Notice
11/19/2018 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
11/02/2018 Application of American Transmission Systems, Incorporated for the Construction Notice of Ashtabula 138 kV Substation Expansion filed by N. Bryksenkova.
10/23/2018 In the matter of the Pre-Application Notification Letter for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.