Case Title: Amendment to East Springfield-Tangy 138kV to Broadview Substation Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BTA-Application to Amend a Certificate/ Gas or Electri
Date Opened: 4/16/2018
Date Closed:
Printable Docket Card Service List
View All
1 - 13 of 13 documents 1 /  1 
Date FiledSummaryPages
05/13/2019Letter stating that these Projects were completed on May 1, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
12/20/2018Letter stating that construction on the East Springfield 138 kV Loop to Broadview Substation Project is expected to begin on approximately January 7, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
11/15/2018Service Notice1
11/15/2018Order on Certificate ordered, That ATSTs First Amendment Application be approved, subject to the conditions set forth in the Certificate Case.6
08/16/2018Service Notice2
08/16/2018Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.4
07/26/2018Corrected Figure 1-10 Revision 1 filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. 2
05/24/2018Proof of Pub of Notice of Filing of Amendment Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.4
05/18/2018Amended Application for the East Springfield - Tangy 138kv Loop to Broadview Substation project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. (Part 4 of 4) 13
05/18/2018Amended Application for the East Springfield - Tangy 138kv Loop to Broadview Substation project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. (Part 3 of 4) 58
05/18/2018Amended Application for the East Springfield - Tangy 138kv Loop to Broadview Substation project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. (Part 2 of 4) 105
05/18/2018Amended Application for the East Springfield - Tangy 138kv Loop to Broadview Substation project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. (Part 1 of 4) 44
04/16/2018In the matter of the pre-application notification letter for an Amendment to the East Springfield-Tangy 138kV Loop to Broadview Substation Project filed by N. Bryksenkova on behalf of FirstEnergy Service Company.1
 