Date Filed | Summary | Pages |
05/26/2020 | Case action form closing case as of 5/26/20, in the Matter of a Request for Upgrades to the Active Warning Devices at Center Street/SR 95 (DOT#518-415T) and Kenton Avenue/SR 309 (DOT#261-540P) in Marion County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. | 2 |
05/26/2020 | Memo Closing Case In the Matter of a Request for Upgrades to the Active Warning Devices at Center Street/SR 95 (DOT#518-415T) and Kenton Avenue/SR 309 (DOT#261-540P) in Marion County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. | 4 |
07/08/2019 | Attorney Examiner Entry granting additional time to complete projects electronically filed by Heather A. Chilcote on behalf of James M. Lynn, Attorney Examiner, Public Utilities Commission of Ohio. | 5 |
07/08/2019 | Service Notice | 2 |
06/21/2019 | Memorandum that Staff recommends another 30 day extension electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. | 5 |
06/19/2019 | Request for 30 day extension electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation. | 2 |
06/19/2019 | Request for 30 day extension electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation. | 2 |
05/23/2019 | Service Notice | 2 |
05/23/2019 | Attorney Examiner Entry granting additional time to complete projects electronically filed by Heather A Chilcote on behalf of James M. Lynn, Attorney Examiner, Public Utilities Commission. | 5 |
05/20/2019 | Memorandum from Staff recommending the Commission grant the 30 day extension request electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. | 4 |
05/14/2019 | Request 30 Day Extension-Marion, Marion Co., OH, Center Street, PID 96927, A46193, DOT 518415T electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation. | 2 |
05/14/2019 | Request 30 Day Extension-Marion, Marion Co., OH, PID 96926, DOT 261540P, A46195 electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation. | 2 |
03/27/2019 | Service Notice | 2 |
03/27/2019 | Entry ordered that CSX's request for additional time to complete the projects be
granted in accordance with Paragraph 15, ordered that CSX complete the projects no later than May 19, 2019, ordered that CSX follow all standard railroad crossing safety protocol to
ensure the protection of the traveling public at the crossings. | 4 |
02/22/2019 | Response to extension request electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division. | 4 |