Date Filed | Summary | Pages |
07/11/2018 | Notice of In-Service Date of 6/12/2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
05/09/2018 | Notification stating that construction commenced on February 22, 2018 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
01/22/2018 | Correspondence (Acceptance of Staff’s Conditions) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
01/19/2018 | Service Notice | 2 |
01/19/2018 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
10/30/2017 | Notice of proof of compliance electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
10/27/2017 | Construction Notice / application electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 82 |
10/13/2017 | In the matter of the Pre-Application Notification Letter of AEP Ohio Transmission Company, Inc. for a Certificate of Environmental Compatibility and Public Need for the Softail Switch 138kV Transmission Line Extension Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 3 |