Date Filed | Summary | Pages |
10/31/2019 | Notice of the Completion of Construction of Project was May 29, 2019 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |
02/26/2018 | Construction notice that this project commenced on February 12, 2018 filed by W. Beutler on behalf of FirstEnergy Service Company. | 1 |
12/14/2017 | Service Notice | 2 |
12/14/2017 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
09/21/2017 | Application for construction notice of West Fremont Substation Expansion Project filed by filed by W. Beutler on behalf of FirstEnergy Service Co. | 33 |
09/01/2017 | In the matter of the Pre-Application Notification Letter electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 2 |