Date Filed | Summary | Pages |
11/13/2017 | Notification to inform that project will be put in service on December 29, 2017 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. | 2 |
02/28/2017 | Notification of Start of Construction for the Harrison-Circleville 138 kV Transmission Line Project
electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
02/09/2017 | Notification of Start of Construction for the Harrison-Circleville 138 kV Transmission Line Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
01/11/2016 | Letter of Notification Accepting Staff Conditions electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 2 |
01/06/2016 | Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. | 7 |
11/03/2015 | Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 4 |
10/15/2015 | Letter of Notification - Appendix, Part 2 of 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 77 |
10/15/2015 | Letter of Notification -Appendix, Part 1 of 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 70 |
10/14/2015 | In the matter of the Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. | 12 |