Date Filed | Summary | Pages |
08/22/2014 | Construction Notice that project was completed on August 15, 2014 filed by S. Humphrys on behalf of First Energy. | 1 |
05/13/2014 | Response to the Letter of Notification on the above captioned
project filed on February 18, 2014 and approved on March 19, 2014 filed by Scott Humphrys on behalf of FirstEnergy Service Company. | 1 |
03/11/2014 | Report of investigation electronically filed by Mr. Adam S. Bargar on behalf of Staff of OPSB. | 3 |
02/26/2014 | Notice of Minor Revision to Letter of Notification electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 6 |
02/18/2014 | In the matter of the Letter of Notification of Lemoyne-Midway 138 kV Transmission Line Tap to Home Depot Substation Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 34 |