DIS - Case Record for 14-0240-EL-BLN Skip to main content
      
      
CASE NUMBER: 14-0240-EL-BLN
CASE DESCRIPTION: Lemoyne-Midway 138 kV Transmission Line Tap to Home Depot Substation
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
08/22/2014 Construction Notice that project was completed on August 15, 2014 filed by S. Humphrys on behalf of First Energy.
05/13/2014 Response to the Letter of Notification on the above captioned project filed on February 18, 2014 and approved on March 19, 2014 filed by Scott Humphrys on behalf of FirstEnergy Service Company.
03/11/2014 Report of investigation electronically filed by Mr. Adam S. Bargar on behalf of Staff of OPSB.
02/26/2014 Notice of Minor Revision to Letter of Notification electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
02/18/2014 In the matter of the Letter of Notification of Lemoyne-Midway 138 kV Transmission Line Tap to Home Depot Substation Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.