Date Filed | Summary | Pages |
06/29/2015 | Letter is in response to the Letters of Notification on the above referenced
projects previously submitted to the Ohio Power Siting Board on September 7, 2012 and January 10, 2014 respectively. Construction on these projects commenced on February 17, 2014 and March 3, 2014 respectively. Please be advised that both projects were placed in service on May 16, 2015 and May 15, 2015 respectively. Site restoration
activities are expected to continue and conclude later in 2015, filed by Theodore Krauss filed by FirstEnergy Service Company. | 1 |
03/04/2014 | Letter of Notification indicated that the tree clearing portion
of construction on the Project was expected to begin as early as approximately February 10, 2014. Please be advised that construction on this Project did not begin on that date and we expect that the clearing work on the Project will commence on Monday March 3, 2014 or
shortly thereafter, filed by Ted Krauss on behalf of FirstEnergy Service Company. | 1 |
02/06/2014 | Notice of Acceptance of Staff's Proposed Conditions on Certificate electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 3 |
01/30/2014 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 5 |
01/22/2014 | Proof of Publication for the county of Jefferson. | 3 |
01/10/2014 | In the matter of the Letter of Notification Toronto and Sammis Area 138 kV Transmission Line Rebuild and Reconfiguration electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 56 |