Summary: |
Letter is in response to the Letters of Notification on the above referenced
projects previously submitted to the Ohio Power Siting Board on September 7, 2012 and January 10, 2014 respectively. Construction on these projects commenced on February 17, 2014 and March 3, 2014 respectively. Please be advised that both projects were placed in service on May 16, 2015 and May 15, 2015 respectively. Site restoration
activities are expected to continue and conclude later in 2015, filed by Theodore Krauss filed by FirstEnergy Service Company. |
|