Date Filed | Summary | Pages |
03/02/2017 | Notification of Construction Start Date and In-Service Date for the North Findlay Station Expansion Project
electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
03/01/2017 | Notification that Construction is Complete and the Facility is In Service for the North Findlay Station Expansion Project
electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
07/17/2015 | Notice of Withdrawal and Substitution of Counsel electronically filed by Mr. Ajay K Kumar on behalf of AEP Ohio Transmission Company. | 3 |
06/04/2015 | Construction Notice stating that the North Findlay Station Expansion Project started on February 1, 2015 electronically filed by Mr. Ajay K. Kumar on behalf of AEP Ohio Transmission Company. | 2 |
09/19/2013 | Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 3 |
08/16/2013 | In the matter of the Construction notification of North Findlay Station Expansion electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 32 |