DIS - Case Record for 11-4884-EL-BTX Skip to main content

Case Record For:

11-4884-EL-BTX

Case Title: AMERICAN TRANSMISSION SYSTEMS INC
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 8/26/2011
Date Closed: 1/11/2016
Printable Docket Card Service List
View All
1 - 15 of 78 documents 1 /  6 
Date FiledSummaryPages
01/11/2016Memo closing cases with an effective date of 1/11/16.1
12/24/2014Letter of Notification that Minor construction activities, primarily maintaining erosion controls while vegetation becomes reestablished in areas disturbed by construction, are still underway and are expected to be completed in Spring 2015 filed by Jessica Thacker on behalf of FirstEnergy Service Company. 1
11/04/2014Access Map Figure 1 Revision electronically filed by Ms. Jessica L Thacker on behalf of FirstEnergy Service Company.2
07/26/2013Letter of Notification of an engineering design change that is being submitted in Case No. 11-4884-EL-BTX, the East Springfield-London-Tangy 138 kV Transmission Line Project filed by Jessica Thacker on behalf of FirstEnergy Service Company. 2
03/11/2013Service Notice4
03/11/2013Opinion, Order and Certificates stating that the Stipulations filed by the parties be approved and adopted and that certificates be issued to ATSI for the construction, operation, and maintenance of the Line Project, along the preferred route, and the Substation Project, at the preferred site.35
01/23/2013Exhibit "applicant's 4" from hearing held on January 23, 2013, filed by American Transmission Systems Incorporated. 3
01/23/2013Transcript of American Transmission Systems, Inc. hearing held before Mr. Bryce McKenney and Ms. Greta See, Administrative Law Judges, at the Public Utilities Commission of Ohio, 180 East Broad Street, Room 11-C, Columbus, Ohio, called at 10 a.m. on Wednesday, January 23, 2013 electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs.33
01/23/2013Joint Exhibit 1-S Joint Stipulation of the Parties for London Substation Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.23
01/23/2013Joint Exhibit 1-L, Joint Stipulation of the Parties for East Springfield London Tangy Transmission Line electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.26
01/17/2013Statement in Lieu of Testimony on Behalf of Nationwide Realty Investors, Ltd. electronically filed by Mr. Christopher W. Michael on behalf of Nationwide Realty Investors, Ltd.4
01/17/2013 Prefiled Testimony of Jim O'Dell on behalf of the Staff of the Ohio Power Siting Board submitted by Assistant Attorney General John H. Jones. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board5
01/16/2013Exhibits from hearing on January 7, 2013.78
01/15/2013Comments of The Nature Conservancy to The Public Utilities Commission of Ohio on the proposed ATSI/First Energy transmission line filed by A.Sasson, Freshwater Conservation Manager. 9
01/14/2013Comments regarding the proposed transmission line project filed by by A. Sasson on behalf of The Nature Conservancy. 9
 
1 /  6 
      
      
Attorney General:
Jones, John
Plantz, Summer
Simmons, Cameron
Attorney Examiner:
See, Greta
McKenney, Bryce