Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
06/04/2012 | Letter in response to the construction notice project filed by Jessica Thacker on behalf of FirstEerngy Service Company. | 1 |
08/29/2011 | Construction notice for the Lemoyne-Maclean 138 kV Transmission Line Reconducting Project filed on behalf of FirstEnergy Service Company by J. Thacker. | 1 |
07/27/2011 | Staff Investigation Report and Recommendation involving the replacement of approximately 7.2 miles of existing 138 kV conductors located in the Village of Pemberville, Troy Township, Lake Township, Freedom Township and Wood County. | 2 |
06/01/2011 | In the matter of the Application for Lemoyne-Maclean #2 138 kV Transmission line reconductoring and intermediate structure installation project filed by J. Thacker on behalf of FirstEnergy Service Company. | 40 |