Date Filed | Summary | Pages |
02/01/2012 | Case Status Form with an effective date of 2/1/12. | 1 |
03/23/2011 | Notice of submission of site plans/cost estimates, and of initiation of utility contract filed by D. Talbott on behalf of Norfolk Southern Railway Company. | 3 |
03/22/2011 | Notice of submission of site plans/cost estimates and of initiation of utility contact filed by D. Casey Talbott on behalf of Norfolk Southern Railway. (FAX) | 3 |
12/15/2010 | Service Notice | 2 |
12/15/2010 | Entry ordering that NS submit to the Commission and ORDC site plans and cost estimates for the projects by March 15, 2011; that NS notify the Commission and ORDC 30 days before the projected date of completion; and staff will file a memorandum in this docket indicating that the installations are completed and the warning devices have been put in service. | 4 |
12/01/2010 | In the matter of the authorization of the Norfolk Southern Railway to install active grade crossing warning devices in Erie and Pickaway Counties. | 18 |