10/02/2013Notice of Active Grade Crossing Warning Devices in Darke County, Village of Ansonia at Jackson Street completion date of 3/1/2012 filed by PUCO Rail Staff, J. Henry.5
10/02/2013Case status form closing case. 1
11/22/2011Service Notice1
11/22/2011Entry ordering that the contract amendment be adopted and approved and the following site plans and cost estimates, CSX proceed with and complete the project on or before April 10, 2012.2
11/07/2011Memo from Staff recommending the Jackson Street Project move forward.5
09/15/2011Memorandum with amendment to ORDC contract requesting to increase their project cost maximum due to the increase in project cost filed on behalf of PUCO Staff, J. Henry.18
08/03/2011Service Notice1
08/03/2011Entry ordering that the completion date of the CSX project be extended until April 10, 2012.2
07/20/2011Letter stating that after additional review and discussion, staff is recommending the project move forward. Due to the delays in getting the plans and estimates, securing approval, and the complex warning system design, Staff request that the project be extended until April 10, 2012 filed by Staff. 1
07/08/2011Service Notice1
07/08/2011Entry ordering that staff's request for a 30-day extension of the completion date be granted. (SF)2
07/07/2011Memo stating that due to the complexity of the project, Staff needs additional time to consider a project timeline, Staff requests the project deadline be extended 30 days so timeline can be determined filed by PUCO Staff, J. Henry.1
11/22/2010Service notice.1
11/19/2010Entry ordered that CSX's request for an extension of time is granted, ordered that CSX submit site plans and cost estimates by December 16, 2010. (SF)2
11/19/2010Letter asking the Commission for an extension until December 16, 2010, due to the complexity of the design for the project filed by Staff. 1
 