Date Filed | Summary | Pages |
03/20/2015 | Case Action Form to Close Cases effective 3/20/2015. | 6 |
11/09/2010 | Letter informing the PUCO that construction on this project was completed on approximately November 2,2010 filed by S. Humphrys on behalf of FirstEnergy Service Company. | 1 |
09/24/2010 | Letter of notification advising that construction on this project to begin on or shortly after after September 27, 2010 filed on behalf of FirstEnergy Service Company by S. Humphrys. | 1 |
07/30/2010 | Staff investigation report and recommendation on the Brookside Cloverdale 138 kV Transmission Line Structure Replacement filed by Staff, J. O'Dell. | 1 |
06/08/2010 | In the matter of the letter of notification, Brookside-Cloverdale 138 kV Transmission Line Structure Replacement. | 23 |