Date Filed | Summary | Pages |
06/06/2013 | Letter of notification informing Commission that construction on this project was completed on approximately May 31, 2013 filed on behalf of FirstEnergy Service Company by S. Humphrys. | 1 |
04/30/2012 | Letter of Notification by FirstEnergy Service Company in response to an inquiry of the status of the Davis Besse Substation Expansion Project filed by Scott M. Humphrys. | 1 |
01/07/2010 | Letter of notification that construction on the Davis Besse Substation Expansion Project was delayed and is to begin as early as January 4, 2010, filed on behalf of FirstEnergy Service Company by S. Humphrys. | 1 |
10/23/2008 | Staff investigation report and recommendations. | 1 |
09/17/2008 | In the matter of the letter of notification of American Transmission Systems, Inc. a subsidiary of FirstEnergy Corp. for the proposed preconfiguration of the Davis Besse substation. | 14 |