DIS - Case Record for 08-0170-EL-BTX Skip to main content

Case Record For:

08-0170-EL-BTX

Case Title: COLUMBUS SOUTHERN POWER COMPANY CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR THE ROBERTS OSU 138KV TRANSMISSION LINE PROJECT
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 2/22/2008
Date Closed: 3/24/2015
Printable Docket Card Service List
View per page
Date FiledSummaryPages
03/24/2015Memo closing case with an effective date of 3/24/15.1
11/08/2013Notice of withdrawal and Substitution of Counsel submitted on behalf of the Staff of the Public Utilities Commission of Ohio. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board3
02/04/2013Case Action Form Reopening Cases electronically filed by Mr. Jeffrey R Jones on behalf of Public Utilities Commission of Ohio.2
09/25/2012Case Action Form to Close cases effective 09/25/2012 filed by J. Jones.1
02/07/2012Notice of Roberts-OSU 138 kV transmission line completed and energized electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc.2
01/05/2012Notice to Ohio Power Siting Board of Roberts-OSU 138 kV Transmission Line Project electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company.2
07/25/2011Service Notice4
07/25/2011Entry ordering that the joint application to transfer the certificate from CSP to Ohio Transco be granted in accordance with Section 4906.04 revised code. 3
05/25/2011Joint Application electronically filed by Erin C Miller on behalf of Columbus Southern Power Company.12
05/25/2011Joint Application electronically filed by Erin C Miller on behalf of Columbus Southern Power Company.12
04/04/2011Response letter sent to John Heppner filed by PUCO Staff.1
03/25/2011Letter to J. Heppner, American Electric Power that Staff concerns regarding HDD under and along the Scioto River have been addressed and installation of said transmission line is authorized to continue from K. Lambeck, OPSB.2
03/25/2011Letter of Notification -- Roberts – OSU 138kV Transmission Line Project Ohio Power Siting Board Update Addendum to Frac Out Plan for Scioto River Directional Drill electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company.4
03/22/2011Correspondence Update Information Re Condition #17 electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company3
01/21/2011Report - OSU-Roberts 138k Transmission Line Project electronically filed by Mr. Matthew J Satterwhite on behalf of American Electric Power Service Corporation.33
01/14/2011Response letter to Mr. John Heppner filed on behalf of the Ohio Power Siting Board by K. Lambeck.1
01/10/2011Notice electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company.11
12/23/2010Response to Mr. John Heppner, American Electric Power Company filed on behalf of OPSB by K. Lambeck.1
12/17/2010Notice of withdrawal of counsel, Sarah J. Parrot and addition of counsel, Stephen A. Reilly filed by Sarah Parrot on behalf of PUCO.3
12/09/2010Response letter sent to John Heppner on behalf of OPSB Staff.1
12/03/2010Letter of Notification electronically filed by Mr. Matthew J. Satterwhite on behalf of Columbus Southern Power Company.13
11/12/2010Ohio EPA General Permit associated with storm water required by the certificate issued by the board in this case filed on behalf of AEP, by S. Nourse.3
11/04/2010Letter including permits required by the certificate issued by the Board including: Notice of Intent (NOI) for coverage under the OEPA General NPDES Permit for authorization to discharge storm water associated with construction activity, the US Army Corp of Engineers crossing permits for the Olentangy and Scioto Rivers and the Storm Water Pollution Prevention Plan (SWPPP), filed by M. Satterwhite on behalf of American Electric Power.110
09/15/2010Notice of withdrawal electronically filed by Mr. Matthew J Satterwhite on behalf of American Electric Power Service Corporation.2
09/02/2010Amendment for the Roberts - OSU 138 kV Line filed by M. Satterwhite on behalf of American Electric Power.19
07/26/2010Notice of withdrawal of counsel filed by Staff. 3
03/23/2010Service Notice4
03/22/2010Order on rehearing stating that the rehearing be denied as set forth herein. (OPSB)5
11/25/2009Correspondence on behalf of American Electric Power in response to the November 5, 2009 letter to the Ohio Power Siting Board filed by M. Satterwhite.2
11/18/2009Service Notice2
11/18/2009Entry ordering that rehearing be granted as outlined in finding (8). (JJ)3
11/12/2009Letter regarding notification deficiencies filed by W. Warner on behalf of Norwich Township.1
10/30/2009Columbus Southern Power Company's memorandum contra the letters filed October 20, 2009 and October 21, 2009 in this docket seeking rehearing filed by M. Satterwhite.10
10/21/2009Letter in support of the application for rehearing filed by many residents of the Highpoint Subdivision. 7
10/21/2009Letter in support of the rehearing request filed by various owners in the Dublin Road area.4
10/20/2009Application for rehearing filed by J. Buchanan on behalf of Quarry Pointe Home Owners Association.6
10/20/2009Letter in support of the Quarry Pointe Homeowners Association's application for rehearing filed by T. Myers on behalf of Stonebrooke Village Board of Directors.7
09/21/2009Service Notice2
09/21/2009Opinion, Order and Certificate approving and adopting the Stipulation filed by the parties; that a certificate be issued to CSP for the construction, operation, and maintenance of the project as proposed along the preferred route. (OPSB)28
07/31/2009Transcript for Columbus Southern Power held 7/17/09 electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Hennebert, Julieanna Mrs.8
07/30/2009Transcript for hearing held July 16, 2009 before AE Jeffrey Jones, Franklin, County electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Columbus Southern Power.8
07/28/2009Exhibits for hearing held 7/14/08 at the City of Upper Arlington Council Chambers before Jeffrey Jones, Attorney Examiner.4
07/28/2009Transcript of hearing held July 14, 2009 before AE J. Jones at the City of Upper Arlington Council Chambers, Franklin County, electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Mrs. Maria DiPaolo Jones.24
07/17/2009Affidavit for Ellen E. Regennitter filed by M. Satterwhite on behalf of American Electric Power.2
07/17/2009Joint stipulation and recommended findings of fact filed by S. Parrot, Assistant AG of the PUCO, M. Malone, Assistant AG of the Environmental Enforcement Agency and M. Satterwhite, Counsel for American Electric Power and J. Valentino, Assistant Mayor, City of Upper Arlington.20
07/16/2009Proof of publication. (Franklin County)7
07/15/2009Correspondence letter supporting the alternate route for the Roberts Road-OSU transmission line, filed by V. Banfield, consumer.1
06/30/2009Service Notice4
06/29/2009Staff report filed.50
06/09/2009Proofs of publication for Upper Arlington and Franklin County submitted on behalf of American Electric Power by S. Nourse.7
05/07/2009Service Notice2
05/06/2009Entry ordering that hearings be scheduled and held on July 14, 2009, at 6:00 p.m., at the City of Upper Arlington Council Chambers, 3600 Tremont Road, Columbus, Ohio 43221. The adjudicatory hearing will commence on July 16, 2009, at 10:00 a.m., in Hearing Room 11-G, at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Columbus, Ohio 43215-3793; that notices of the application and hearings be published by CSPC in accordance with finding (4); that the City of Upper Arlington be granted intervention in accordance with finding (7). (JRJ)3
04/09/2009Letter asking the Commission to accept certification of compliance with the service requirements filed by M. Satterwhite on behalf of Columbus Southern Power Company. 16
04/06/2009Response to the staff's questions/clarifacations (Set #3) docketed on March 20, 2009, filed by M. Satterwhite on behalf of American Electric Power Service Corporation. 24
03/20/2009Response letter to: Pete Elwell on behalf of the Ohio Power Siting Board filed by K. Lambeck. 2
02/27/2009Letter to P. Elwell, AEP, regarding the OSU 138 kV Transmission Line Project from A. Schriber, OPSP.2
02/12/2009Motion to intervene and memorandum in support of the City of Upper Arlington, Ohio filed by W. Adams. 4
02/06/2009Response to the Staff's questions and clarification docketed on January 23, 2009, filed by S. Nourse on behalf of Columbus Southern Power Company. 6
02/06/2009Response to the Staff's questions and clarifications docketed on January 26, 2009, filed by S. Nourse on behalf of Columbus Southern Power Company. 8
02/02/2009Service Notice1
02/02/2009Entry granting CSPC's motion for a waiver of the requirement; that an application be filed at least one year prior to the planned date of commencement of construction. (JRJ)2
01/29/2009Letter stating Staff does not object to the applicant's request for waiver but reserves the right to investigate and contest any other issue presented in the application filed by A. Hammerstein.1
01/26/2009Response letter to: Ellen Regennitter, on behalf of the Ohio Power Siting Board filed by K. Lambeck. 3
01/23/2009Correspondence sent to; Ms. Ellen Regennitter with Staff questions and clarifications for the proposed AEP Roberts-OSU transmission line application as submitted December 30, 2008, requesting responses by February 6, 2009 filed by OPSB Staff, K. Lambeck.2
12/30/2008Application continued. (PART 2 of 2)67
12/30/2008Application for a certificate of environmental compatibility and public need for the Roberts-OSU 138 kV Transmission Line Project field by A. Smith on behalf of Columbus Southern Power. (Part 1 of 2)201
12/30/2008Motion for waiver and memorandum in support filed M. Satterwhite on behalf of Columbus Southern Power Company.3
02/22/2008In the matter of the application of Columbus Southern Power Company for a certificate of environmental compatibility and public need for the Roberts-OSU 138kV transmission line project. 1