03/24/2015
|
Memo closing case with an effective date of 3/24/15. |
11/08/2013
|
Notice of withdrawal and Substitution of Counsel submitted on behalf of the Staff of the Public Utilities Commission of Ohio. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board |
02/04/2013
|
Case Action Form Reopening Cases electronically filed by Mr. Jeffrey R Jones on behalf of Public Utilities Commission of Ohio. |
09/25/2012
|
Case Action Form to Close cases effective 09/25/2012 filed by J. Jones. |
02/07/2012
|
Notice of Roberts-OSU 138 kV transmission line completed and energized electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. |
01/05/2012
|
Notice to Ohio Power Siting Board of Roberts-OSU 138 kV Transmission Line Project electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
07/25/2011
|
Service Notice |
07/25/2011
|
Entry ordering that the joint application to transfer the certificate from CSP to Ohio Transco be granted in accordance with Section 4906.04 revised code. |
05/25/2011
|
Joint Application electronically filed by Erin C Miller on behalf of Columbus Southern Power Company. |
05/25/2011
|
Joint Application electronically filed by Erin C Miller on behalf of Columbus Southern Power Company. |
04/04/2011
|
Response letter sent to John Heppner filed by PUCO Staff. |
03/25/2011
|
Letter to J. Heppner, American Electric Power that Staff concerns regarding HDD under and along the Scioto River have been addressed and installation of said transmission line is authorized to continue from K. Lambeck, OPSB. |
03/25/2011
|
Letter of Notification -- Roberts – OSU 138kV Transmission Line Project Ohio Power Siting Board Update Addendum to Frac Out Plan for Scioto River Directional Drill electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company. |
03/22/2011
|
Correspondence Update Information Re Condition #17 electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company |
01/21/2011
|
Report - OSU-Roberts 138k Transmission Line Project electronically filed by Mr. Matthew J Satterwhite on behalf of American Electric Power Service Corporation. |
01/14/2011
|
Response letter to Mr. John Heppner filed on behalf of the Ohio Power Siting Board by K. Lambeck. |
01/10/2011
|
Notice electronically filed by Mr. Matthew J Satterwhite on behalf of Columbus Southern Power Company. |
12/23/2010
|
Response to Mr. John Heppner, American Electric Power Company filed on behalf of OPSB by K. Lambeck. |
12/17/2010
|
Notice of withdrawal of counsel, Sarah J. Parrot and addition of counsel, Stephen A. Reilly filed by Sarah Parrot on behalf of PUCO. |
12/09/2010
|
Response letter sent to John Heppner on behalf of OPSB Staff. |
12/03/2010
|
Letter of Notification electronically filed by Mr. Matthew J. Satterwhite on behalf of Columbus Southern Power Company. |
11/12/2010
|
Ohio EPA General Permit associated with storm water required by the certificate issued by the board in this case filed on behalf of AEP, by S. Nourse. |
11/04/2010
|
Letter including permits required by the certificate issued by the Board including: Notice of Intent (NOI) for coverage under the OEPA General NPDES Permit for authorization to discharge storm water associated with construction activity, the US Army Corp of Engineers crossing permits for the Olentangy and Scioto Rivers and the Storm Water Pollution Prevention Plan (SWPPP), filed by M. Satterwhite on behalf of American Electric Power. |
09/15/2010
|
Notice of withdrawal electronically filed by Mr. Matthew J Satterwhite on behalf of American Electric Power Service Corporation. |
09/02/2010
|
Amendment for the Roberts - OSU 138 kV Line filed by M. Satterwhite on behalf of American Electric Power. |
07/26/2010
|
Notice of withdrawal of counsel filed by Staff. |
03/23/2010
|
Service Notice |
03/22/2010
|
Order on rehearing stating that the rehearing be denied as set forth herein. (OPSB) |
11/25/2009
|
Correspondence on behalf of American Electric Power in response to the November 5, 2009 letter to the Ohio Power Siting Board filed by M. Satterwhite. |
11/18/2009
|
Service Notice |
11/18/2009
|
Entry ordering that rehearing be granted as outlined in finding (8). (JJ) |
11/12/2009
|
Letter regarding notification deficiencies filed by W. Warner on behalf of Norwich Township. |
10/30/2009
|
Columbus Southern Power Company's memorandum contra the letters filed October 20, 2009 and October 21, 2009 in this docket seeking rehearing filed by M. Satterwhite. |
10/21/2009
|
Letter in support of the application for rehearing filed by many residents of the Highpoint Subdivision. |
10/21/2009
|
Letter in support of the rehearing request filed by various owners in the Dublin Road area. |
10/20/2009
|
Application for rehearing filed by J. Buchanan on behalf of Quarry Pointe Home Owners Association. |
10/20/2009
|
Letter in support of the Quarry Pointe Homeowners Association's application for rehearing filed by T. Myers on behalf of Stonebrooke Village Board of Directors. |
09/21/2009
|
Service Notice |
09/21/2009
|
Opinion, Order and Certificate approving and adopting the Stipulation filed by the parties; that a certificate be issued to CSP for the construction, operation, and maintenance of the project as proposed along the preferred route. (OPSB) |
07/31/2009
|
Transcript for Columbus Southern Power held 7/17/09 electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Hennebert, Julieanna Mrs. |
07/30/2009
|
Transcript for hearing held July 16, 2009 before AE Jeffrey Jones, Franklin, County electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Columbus Southern Power. |
07/28/2009
|
Exhibits for hearing held 7/14/08 at the City of Upper Arlington Council Chambers before Jeffrey Jones, Attorney Examiner. |
07/28/2009
|
Transcript of hearing held July 14, 2009 before AE J. Jones at the City of Upper Arlington Council Chambers, Franklin County, electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Mrs. Maria DiPaolo Jones. |
07/17/2009
|
Affidavit for Ellen E. Regennitter filed by M. Satterwhite on behalf of American Electric Power. |
07/17/2009
|
Joint stipulation and recommended findings of fact filed by S. Parrot, Assistant AG of the PUCO, M. Malone, Assistant AG of the Environmental Enforcement Agency and M. Satterwhite, Counsel for American Electric Power and J. Valentino, Assistant Mayor, City of Upper Arlington. |
07/16/2009
|
Proof of publication. (Franklin County) |
07/15/2009
|
Correspondence letter supporting the alternate route for the Roberts Road-OSU transmission line, filed by V. Banfield, consumer. |
06/30/2009
|
Service Notice |
06/29/2009
|
Staff report filed. |
06/09/2009
|
Proofs of publication for Upper Arlington and Franklin County submitted on behalf of American Electric Power by S. Nourse. |
05/07/2009
|
Service Notice |
05/06/2009
|
Entry ordering that hearings be scheduled and held on July 14, 2009, at 6:00 p.m., at the City of Upper Arlington Council Chambers, 3600 Tremont Road, Columbus, Ohio 43221. The adjudicatory hearing will commence on July 16, 2009, at 10:00 a.m., in Hearing Room 11-G, at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Columbus, Ohio 43215-3793; that notices of the application and hearings be published by CSPC in accordance with finding (4); that the City of Upper Arlington be granted intervention in accordance with finding (7). (JRJ) |
04/09/2009
|
Letter asking the Commission to accept certification of compliance with the service requirements filed by M. Satterwhite on behalf of Columbus Southern Power Company. |
04/06/2009
|
Response to the staff's questions/clarifacations (Set #3) docketed on March 20, 2009, filed by M. Satterwhite on behalf of American Electric Power Service Corporation. |
03/20/2009
|
Response letter to: Pete Elwell on behalf of the Ohio Power Siting Board filed by K. Lambeck. |
02/27/2009
|
Letter to P. Elwell, AEP, regarding the OSU 138 kV Transmission Line Project from A. Schriber, OPSP. |
02/12/2009
|
Motion to intervene and memorandum in support of the City of Upper Arlington, Ohio filed by W. Adams. |
02/06/2009
|
Response to the Staff's questions and clarification docketed on January 23, 2009, filed by S. Nourse on behalf of Columbus Southern Power Company. |
02/06/2009
|
Response to the Staff's questions and clarifications docketed on January 26, 2009, filed by S. Nourse on behalf of Columbus Southern Power Company. |
02/02/2009
|
Service Notice |
02/02/2009
|
Entry granting CSPC's motion for a waiver of the requirement; that an application be filed at least one year prior to the planned date of commencement of construction. (JRJ) |
01/29/2009
|
Letter stating Staff does not object to the applicant's request for waiver but reserves the right to investigate and contest any other issue presented in the application filed by A. Hammerstein. |
01/26/2009
|
Response letter to: Ellen Regennitter, on behalf of the Ohio Power Siting Board filed by K. Lambeck. |
01/23/2009
|
Correspondence sent to; Ms. Ellen Regennitter with Staff questions and clarifications for the proposed AEP Roberts-OSU transmission line application as submitted December 30, 2008, requesting responses by February 6, 2009 filed by OPSB Staff, K. Lambeck. |
12/30/2008
|
Application continued. (PART 2 of 2) |
12/30/2008
|
Application for a certificate of environmental compatibility and public need for the Roberts-OSU 138 kV Transmission Line Project field by A. Smith on behalf of Columbus Southern Power. (Part 1 of 2) |
12/30/2008
|
Motion for waiver and memorandum in support filed M. Satterwhite on behalf of Columbus Southern Power Company. |
02/22/2008
|
In the matter of the application of Columbus Southern Power Company for a certificate of environmental compatibility and public need for the Roberts-OSU 138kV transmission line project. |