Date Filed | Summary | Pages |
07/25/2008 | Memo closing case with an effective date of 7/25/08. | 1 |
07/10/2008 | Service Notice | 1 |
07/10/2008 | Entry ordered that an extension to time to complete the project be granted ; that the Mogadore Road project be completed by July 25, 2008. (SF) | 2 |
07/09/2008 | Letter of a formal request to extend the installation deadline up to 30-days to allow for a delay in electric service connection filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company. | 1 |
07/09/2008 | Memo stating that Wheeling & Lake Railway filed in this docket a request for a 30-day extension of time to complete the installation of the grade crossing project at Portage County, near Brimfield, Mogadore Road, DOT#472-651P, filed by G. Martin, PUCO staff. | 3 |
07/11/2007 | Service Notice | 1 |
07/11/2007 | Entry ordering that W&LE submit to the Commission and ORDC site plans and cost estimates for the project by October 11, 2007; that by October 18, 2007, a letter be filed in this docket advising that site plans and cost estimates have been submitted; that the project should be completed by July 11, 2008. | 4 |
06/29/2007 | In the matter of the application for authorization of the Wheeling & Lake Erie Railway to install an active grade crossing warning device in Portage County. | 9 |