Summary: |
Entry ordering that W&LE submit to the Commission and ORDC site plans and cost estimates for the project by October 11, 2007; that by October 18, 2007, a letter be filed in this docket advising that site plans and cost estimates have been submitted; that the project should be completed by July 11, 2008. |
|