06/02/2008
|
Staff's biennial review and recommendations concerning the controllable RTO costs of FirstEnergy filed by R. Fortney. |
05/01/2008
|
Motion of Ohio Edison Company, the Cleveland Electric Illuminating Company and the Toledo Edison Company for authority to deviate from a Commission approved stipulation and memorandum in support filed by K. Kolick on behalf of Applicant Companies. (original) |
05/01/2008
|
Revised tariff pages, Transmission and Ancillary Service Riders, filed by K. Kolich on behalf of Ohio Edison Company, the Cleveland Electric Illuminating Company and the Toledo Edison Company. |
04/30/2008
|
Motion of Ohio Edison Company, the Cleveland Electric Illuminating Company and the Toledo Edison Company for authority to deviate from a Commission approved stipulation and memorandum in support filed by K. Kolich on behalf of Applicant Companies. (FAX) |
05/31/2007
|
Motion to file reply and to request resolution of issues contingent upon review of additional filing, memorandum in support filed by J. Roberts on behalf of OCC. |
05/01/2007
|
Revised Transmission and Ancillary Service Riders for Ohio Edison Company, The Cleveland Electric Illuminating Company and Ohio Edison Company filed by K. Kolich. |
03/08/2007
|
Notice of withdrawal from intervention, filed on behalf of the Ohio Energy Group by M. Kurtz. |
03/05/2007
|
Memorandum contra Ohio Energy Group motion to intervene, filed on behalf of Ohio Edison Company, The Toledo Edison Company and The Cleveland Electric Illuminating Company by K. Kolich. |
03/05/2007
|
Motion to intervene and memorandum in support, filed on behalf of the office of the Ohio Consumers' Counsel by J. Lake Roberts. |
03/02/2007
|
Memorandum contra Ohio Energy Group motion to intervene on behalf of FirstEnergy, filed by K. Kolich. (FAX) |
02/16/2007
|
Motion for leave to intervene and memorandum in support filed by M. Kurtz Esq. on behalf of Ohio Energy Group. |
02/14/2007
|
Finding and Order; ordered that the February 1, 2007 Stipulation, as submitted by the parties, is approved, as modified by Finding (21); that the Companies' current Transmission and Ancillary Service Riders, which were effective July 1, 2006, under the automatic approval process, are subject to reconciliation based on a continuing review of in the Companies' Transmission and Ancillary Service Riders; that Commission staff perform a biennial review of the Companies' controllable costs, as fully set forth in Staff's Review and Recommendations filed on February 1, 2007; that the Commission's docketing division incorporate the Companies April 27, 2006 application, and the subsequent pleadings, through this Finding and Order into the new docket under Case No. 07-128-EL-ATA; that the Companies, and any party in this proceeding, file all pleadings related to this Finding and Order under Case No. 07-128-EL-ATA; that the Companies file any future adjustment applications for their Transmission and Ancillary Service Riders under Case No. 07-128-EL-ATA; that Case No. 04-1932-EL-ATA be closed of record. |
02/14/2007
|
Service Notice |
02/06/2007
|
In the Matter of the Application of Ohio Edison Company, the Cleveland Electric Illuminating Company, and the Toledo Edison Company for approval of a rider for the collection of RTO costs and transmission and ancillary service costs and for accounting authority to modify their accounting procedures. |