DIS - Case Record for 06-0444-GA-BTX Skip to main content

Case Record For:

06-0444-GA-BTX

File a Public Comment
Case Title: CINCINNATI GAS & ELECTRIC COMPANY DBA DUKE ENERGY OHIO
Status: OPEN-OPEN
Industry Code: GA-GAS
Purpose Code: BTX-Application for a Certificate/ Gas or Electric
Date Opened: 3/20/2006
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
09/16/2013Notice of withdrawal of Counsel submitted by Assistant Attorney General Stephen A. Reilly on behalf of the Staff of the Ohio Power Siting Board. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board.4
12/16/2008Letter stating the construction on the C338 Ohio River to Bethel Natural Gas Pipeline Project was completed on November 17, 2008 filed by S. Lane on behalf of Duke Energy.1
05/21/2007Letter stating that Duke Energy Ohio, Inc and Staff of the Ohio Power Siting Board have reviewed the stipulation for completeness and have determined that further clarification may be useful for the Power Sitting Board filed by R. D'Ascenzo on behalf of Duke Energy Shared Services, Inc. and Staff.3
05/21/2007Service Notice2
05/21/2007Opinion and Order, ordered that the stipulation filed on April 4, 2007, in this matter be approved and adopted. 37
05/08/2007Clarifying additional information filed by R. D'Ascenzo on behalf of Duke Energy Shared Services, Inc. and W. Margard, Staff of Ohio Power Siting Board.3
05/07/2007Correspondence to: Jeanne Kingery, AE, PUCO stating that DE-Ohio and Staff have reviewed the Stipulation for completeness, and have decided that further clarification may be useful for the Power Siting Board filed on behalf of Duke Energy Shared Services by R. D'Ascenzo and Staff of The Ohio Power Siting Board by W. Margard, AG.3
04/19/2007Transcript and exhibits for hearing held April 5, 2007, before Jeanne Kingery Hearing Examiner.50
04/05/2007 Corrected Joint Stipulation filed by P. Colbert on behalf of Duke Energy Ohio, Inc.25
04/05/2007Corrected Direct testimony of Stephen R. Lane on behalf of Duke Energy Ohio, Inc. filed by P. Colbert. 19
04/04/2007Direct testimony Stephen R. Lane on behalf of Duke Energy Ohio filed by R. D'Ascenzo.17
04/04/2007Joint stipulation and recommended findings of fact and conclusion of law filed by R. D'Ascenzo on behalf of Duke Energy Shared Services, Inc. and W. Maggard and L. Angel, OPSB.23
03/29/2007Staff report of investigation, addendum.14
03/26/2007Transcript with exhibits held in Community Center, Bethel, Ohio on March 14, 2007 before Honorable Gregory A. Price.34
03/23/2007Proof of Publication, Cincinnati Post (Hamilton County), Cincinnati Enquirer (Hamilton County), Community Journal Clermont (Hamilton County), Milford Miami Advocate (Hamilton County), Bethel Journal (Hamilton County), and Community Journal North Clermont (Hamilton County), filed on behalf of Duke Energy by A. Schafer.15
03/23/2007Letter in response to the questions and concerns raised by the Anthony V. Macke Limited Partnership in regard to the Rockies Express Pipeline project filed by R. D'Ascenzo on behalf of Duke Energy Ohio, Inc.6
03/01/2007Service Notice2
02/28/2007Entry ordering that the hearings in this matter be scheduled at the times and places designated in finding (9) and that notices of the hearings be made by Duke in accordance with finding (10).3
02/27/2007Final application clarifications for the C 338 Ohio River to Bethel Natural Gas Pipeline project filed by S. Lane on behalf of Duke Energy.6
01/26/2007Correspondence requesting PUCO for an application clarification, the clarification figure specifies a new location for the northern pressure reducing station approximately 850 feet southeast of the location as given the application filed May 1, 2006 filed on behalf of Duke Energy by S. Lane.3
01/23/2007Application Clarifications for the C 338 Ohio River to Bethel Natural Gas Pipeline Project, filed on behalf of Duke Energy by S. Lane.8
11/29/2006Letter concerning and opposing to the recommendations being proposed filed by K. and D. Macke on behalf of Anthony V. Macke Limited Partnership.5
11/15/2006Report providing additional engineering and design information filed by R. D'Ascenzo on behalf of Duke Energy Ohio.26
10/12/2006Transcript and exhibits for hearing held on September 26, 2006, before Honorable Jeanne W. Kingery.58
10/10/2006Transcript for hearing held September 28, 2006, before Ms. Jeanne Kingery, Hearing Examiner.5
09/26/2006Motion for continuance of hearing and change in testimony due date and memorandum in support filed by R. D'Ascenzo on behalf of Duke Energy Ohio.6
09/22/2006Letter requesting permission to intervene and speak at the adjudicatory hearing scheduled for Thursday September 28, 2008 filed by D. Macke.2
09/20/2006Correspondence letter's requesting permission to intervene and speak at the adjudicatory hearing filed by J. Howard.14
09/12/2006Letter submitted to landowners along the route of proposed C338 Ohio River and Bethel Natural gas pipeline project, also a list of contacted landowners filed by S. Lang on behalf of Duke Energy.5
09/07/2006Service Notice3
09/06/2006Staff report of investigation.50
08/03/2006Application clarifications for the C 338 Ohio River to Bethel Natural Gas Pipeline Project filed by S. Lane on behalf of Duke Energy.44
07/26/2006Letter regarding the application fee filed by S. Lane on behalf of Duke Energy.1
07/18/2006Service Notice1
07/17/2006Entry ordered; that hearings in this matter be scheduled at the times and places designated in finding (3); that notices of the hearings be made by Duke in accordance with finding (4); that the Board will accept petitions to intervene in the adjudicatory hearing by interested persons up to five days prior to the scheduled date for the nonadjudicatory hearing, or later if good cause is shown, in accordance with finding (5). (JWK)2
07/12/2006Proof of service of the certified application on the officials and the local public library filed on behalf of Duke Energy by A. Schafer.8
07/06/2006Letter stating that the application has been found to comply with Chapters 4906-01, et seq. filed by the Chairman Alan Schriber.2
07/05/2006Service Notice1
07/03/2006Entry ordering that the Duke's motion for a waiver of Rule 4906-5-04(A), O.A.C.be granted. (JK)3
06/27/2006Staff response to applicant's waiver request filed by K. Lembeck on behalf of staff.2
06/02/2006Additional information for report on behalf of URS Corporation for the C338 Ohio River to Bethel Natural Gas Pipeline Project filed by S. Lane.1
05/01/2006Application for certificate. (Part 4 of 4)70
05/01/2006Application for certificate. (Part 3 of 4)197
05/01/2006Application for certificate. (Part 2 of 2)202
05/01/2006Application for a certificate of environmental compatibility and public need filed by P. Walker on behalf of The Cincinnati Gas & Electric Company dba Duke Energy Ohio, Inc.(Part 1 of 4).201
04/28/2006Motion for waiver by The Cincinnati Gas and Electric Company dba Duke Energy Ohio, Inc. and memorandum in support filed by A. Schafer.66
03/20/2006In the matter of the application of The Cincinnati Gas & Electric Company for a Certificate of Environmental Compatibility and Public Need to construct a 12-inch Natural Gas Pipeline for the Ohio River to Bethel, Ohio.1