Date Filed | Summary | Pages |
09/15/2006 | Memo stating that the grade crossing improvements/upgrades ordered and or agreed been completed and installed filed by PUCO staff G. Martin. | 1 |
03/01/2006 | Letter stating the plan and estimate for the referenced project has been reviewed and is acceptable filed by T. Perkins on behalf of the Ohio Rail Development Commission. | 2 |
03/01/2006 | Letter stating the plan and estimate for the referenced project has been reviewed and is acceptable filed by T. Perkins on behalf of the Ohio Rail Development Commission. | 2 |
03/01/2006 | Letter stating the plan and estimate for the referenced project has been reviewed and is acceptable filed by T. Perkins on behalf of the Ohio Rail Development Commission. | 2 |
12/14/2005 | Letter detailing cost estimate for the installation of active warning devices filed by B. Konrad on behalf of Indiana and Ohio Central Railroad. | 1 |
09/14/2005 | Entry ordering that CSX and I & O submit to the Commission and ORDC site plans and cost estimates for the projects within 90 days of the date of this entry and that following approval, construction proceed and be completed by September 14, 2006 and once project is complete, staff will make final inspection and file a memorandum in this docket directing the docketing division to close this case of record. | 4 |
09/14/2005 | Service Notice | 3 |
09/01/2005 | In the matter of the authorization of the Indiana & Ohio Railway and CSX Transportation to engage in a Corridor Project. | 8 |