07/13/2005 | Entry ordering that CSX submit to the Commission and ORDC site plans and cost estimates for the project by October 13, 2005; that by October 20, 2005 CSX file a letter in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates by ORDC, CSX proceed with construction of the project, with construction to be completed by July 13, 2006; that CSX notify the Commission and ORDC 30 days before the projected date of completion. | 3 |